Gas Exploration - Stages of Gas Well Drilling Production Stage 1: Well Site Surveyed and Staked, Duration: 1-6 months Stage 2: Well Site Being Prepared for Rig Setup, Duration: 1-3 weeks
Stage 3: Rig Set Up at Location for 30 Days, Duration: 30 days Stage 4: Tank Site Before Landscaping is Completed, Duration: 4-12 months
Stage 5: Tank Site After Landscaping is Completed |
|||