District 13


​District 13 Street Update


  • Dallas Water Utilities is constructing new water and wastewater mains from LBJ FWY & Dallas North Tollway South to Northaven Road All of wastewater pipeline has been installed up to the east side of the Dallas North Tollway at Harvest Hill Road. Paving on Northaven Road is complete and minor repairs on Willow Lane are underway. Paving of the outside lanes on Inwood Road from Northaven Road to Forest Lane is complete. Paving on Inwood Road from Forest Lane to Willow Lane is expected to be complete by middle of February. DWU contractor is currently in the process of completing paving in the concrete channel behind Jesuit and St. Rita’s. Once paving in the channel is complete, the contractor will move back to Inwood Road to complete sections of the middle lane between Northaven Road and Forest Lane. Entire project including wastewater section east of Dallas North Tollway and across LBJ Freeway is expected to be complete in summer 2018, weather permitting.   For more information, please click the following link:  Project Information Sheet (February 2018 Update)
  • Dallas Water Utilities has a pipeline replacement project on Lomo Alto Drive from alley south of Sherry Lane to north of Colgate Avenue (PID 4761). DWU contractor has finished pipeline installation and testing and is currently working on final tie-in connections. Entire project including final paving and surface restoration is expected to be complete in March 2018, weather permitting.

  • Dallas Water Utilities is constructing new water and wastewater mains from Preston Road northeast (PID 4954) in the easement.  The contractor will begin working in this area during the third week of November 2017 and is scheduled to be completed spring 2017.  For more information, please click the following link: Dist 11 13 Easement west of Camellia Drive

  • Dallas Water Utilities is constructing new water and wastewater mains on Prestonshire Lane  from Edgemere Road to Hillcrest Road (PID #5531). DWU contractor has finished pipeline installation and is scheduled to start paving around middle of March. Entire project including final paving and surface restoration is expected to be complete in April 2018, weather permitting. For more information, please click the following link: Prestonshire Lane

  • Dallas Water Utilities is constructing new water and wastewater mains on Preston Park Drive from Stanford Avenue to Lovers Lane (PID #3023). DWU contractor has finished pipeline installation and is scheduled to start paving before the end of February. Entire project including final paving and surface restoration is expected to be complete in April 2018, weather permitting. For more information, please click the following link: Preston Park Drive

  • Dallas Water Utilities has a pipeline replacement project on Pebblebrook Drive from Inwood Road west (PID 2878). DWU contractor has finished pipeline installation and is scheduled to start paving before the end of February. Entire project including final paving and surface restoration is expected to be complete in April 2018, weather permitting. For more information, please click the following link:  Pebblebrook Drive

  • Dallas Water Utilities is constructing new water and wastewater mains on Royal Lane from Cromwell Drive west (PID #4616).  The contractor began working in this area the week of April 24, 2017 and is scheduled to be completed the end of spring 2018. DWU contractor has finished pipeline installation and testing and is currently working on paving restorations. Entire project including final paving and surface restoration is expected to be complete in March 2018, weather permitting .For more information on this project, please click the following link:  Royal Lane 
  • Dallas Water Utilities is constructing new water and wastewater mains on  Lovers Lane from Taos Road to Elsby Avenue (PID #4801). The contractor will began working in this area the week of October 23, 2017 and is scheduled to be complete during the winter of 2017/2018.  For more information on this project, please click on the following link:  Lovers Lane
  • Dallas Water Utilities is constructing new water and wastewater mains on Taos Road from Lovers Lane south (PID #4802). DWU contractor has finished pipeline installation and testing and currently is in process to complete transfer of water services and tie-in connections. Entire project including final paving and surface restoration is expected to be complete in April 2018, weather permitting. For more information on this project, please click on the following link:Taos Road
  • Dallas Water Utilities has scheduled a pipeline replacement project on Whirlaway Road from Webb Chapel Road to Webb Garden Drive. DWU contractor has finished pipeline installation and testing and is currently working on final tie-in connections. Entire project including final paving and surface restoration is expected to be complete in March 2018, weather permitting.For more information on this project, please click  on the following link: Whirlaway Road.
  • Dallas Water Utilities has a pipeline replacement project on Skillman Street from Abrams Road to Southwestern Blvd (PIDs 4923 and 4925). DWU contractor has finished approximately 85% of pipeline installation and contractor is currently in the process of scheduling paving on Southwestern Blvd. Entire project including final paving and surface restoration is expected to be complete during spring 2018, weather permitting. For more information on this project, please click Skillman Street