  • Dallas Water Utilities is constructing new water and wastewater mains on Townsend Drive from Cox Lane to Vinecrest Dr. (PID 5498) The contractor will mobilize and begin working in this area during the week of July 30, 2018 and is scheduled to be complete during the winter of 2018.   For more information, please click the following link: Townsend Drive
  • Dallas Water Utilities is constructing new water and wastewater mains from LBJ FWY & Dallas North Tollway South to Northaven Road.

    The contractor has completed all work from Northaven Road to the southeast corner of the Dallas North Tollway and LBJ.  This includes pipe installation and final paving restoration.  The contractor is currently working on the tunnel that goes under LBJ Freeway.  We expect the tunnel section under LBJ to be completed in August 2018, weather permitting.  Once the section under LBJ is complete, the contractor will work to complete the final portion of the project that runs along the south frontage road of LBJ.  Overall, the expected project completion date is October 2018, barring any unforeseen issues.  For more information, please click the following link: Project Information Sheet (April 2018 Update) - DWU Contract 16-324

  • Dallas Water Utilities has a pipeline replacement project on Lomo Alto Drive from alley south of Sherry Lane to north of Colgate Avenue (PID 4761). DWU contractor has finished pipeline installation and is currently working on the paving restoration. Entire project including final paving and surface restoration is expected to be complete in April 2018, weather permitting.

  • Dallas Water Utilities is constructing new water and wastewater mains on State Highway 289 (Preston Road) from Walnut Hill Lane to Royal Lane (PID 4953). This project is scheduled to start in April 2018 and be completed during the winter of 2018/2019. For more information, please click the following link:  State Highway 289 Preston Road

  • Dallas Water Utilities has a pipeline replacement project in the easement south of Orchid Lane from SH289 (Preston Road) East (PID 4957). DWU contractor is in the process of scheduling final paving restorations. Entire project including final paving and surface restoration is expected to be complete in Summer 2018, weather permitting.

  • Dallas Water Utilities has a pipeline replacement project in the easement west of Camellia Drive from State Highway 289 (Preston Road) to north of Royal Lane (PID 4954). DWU contractor has finished pipeline installation and currently is in the process of completing water testing, sampling and service tie-ins. Entire project including final paving and surface restoration is expected to be complete in May 2018, weather permitting.

  • Dallas Water Utilities has a pipeline replacement project on Royal Lane from Cromwell Drive West (PID 4616). DWU contractor has completed the utility construction and paving restoration. The contractor is in the final stages of replacing sod impacted by construction.  Project is expected to be complete in April 2018.

  • Dallas Water Utilities has a pipeline project on Royal Lane from Cox Lane east (PID 2534). Work is scheduled to start in April 2018 and be completed in Fall 2018.

  • Dallas Water Utilities is constructing new water and wastewater mains on Prestonshire Lane  from Edgemere Road to Hillcrest Road (PID #5531). DWU contractor has finished pipeline installation and has been released to complete final paving restoration. Entire project including final paving and surface restoration is expected to be complete by late May 2018, weather permitting. For more information, please click the following link: Prestonshire Lane

  • Dallas Water Utilities is constructing new water and wastewater mains on  Lovers Lane from Taos Road to Elsby Avenue (PID #4801). The contractor has finished pipeline installation and has been released to complete final paving restorations. Due to weather impacts on paving, the project is expected to be comple by late May, 2018, weather permitting.  For more information on this project, please click on the following link: Lovers Lane

  •  Dallas Water Utilities is constructing new water and wastewater mains on Taos Road from Lovers Lane south (PID #4802). DWU contractor has finished pipeline installation and testing and currently is in process to complete transfer of water services and tie-in connections. Entire project including final paving and surface restoration is expected to be complete in April 2018, weather permitting. For more information on this project, please click on the following link:Taos Road

  • Dallas Water Utilities has a pipeline replacement project in the Alley between Amherst Avenue and Lovers Lane from Linwood Avenue to Menier Street (PID 1206). DWU contractor has finished pipeline installation and currently is in the process of completing water tie-ins to the existing mains. Entire project including final paving and surface restoration is expected to be complete in late May 2018, weather permitting.