  • Dallas Water Utilities is constructing new water and wastewater mains from LBJ FWY & Dallas North Tollway South to Northaven Road.

    The contractor has completed all work from Northaven Road to the southeast corner of the Dallas North Tollway and LBJ.  This includes pipe installation and final paving restoration.  The contractor is currently working on the tunnel that goes under LBJ Freeway.  We expect the tunnel section under LBJ to be completed in August 2018, weather permitting.  Once the section under LBJ is complete, the contractor will work to complete the final portion of the project that runs along the south frontage road of LBJ.  Overall, the expected project completion date is October 2018, barring any unforeseen issues.  For more information, please click the following link: Project Information Sheet (April 2018 Update) - DWU Contract 16-324


  • Dallas Water Utilities is constructing new water and wastewater mains on State Highway 289 (Preston Road) from Walnut Hill Lane to Royal Lane (PID 4953).  DWU has a pipeline replacement project under construction at Preston Road from Walnut Hill Lane to Royal Lane that includes approximately 3,760 feet of water and 5,020 feet of wastewater mains.  The contractor has completed about 75 percent of the wastewater installation in Preston Road and is expected to reach the intersection of Preston Road and Royal Lane by March 2019.  Work at the intersection of Preston Road/Royal Lane is expected to take about one month to finish due to the heavy volume of traffic and limited work hours.  DWU is currently working with Traffic Control personnel regarding work restrictions at the intersection, and the expectation is that work will be restricted to night time hours due to the volume of traffic and safety concerns.  Once these working restrictions are confirmed, an additional update will be provided along with efforts to inform local residents that may be affected by the night time work. After completion of work at the intersection, the contractor plans to utilize two crews: one crew to install new water and wastewater mains in Royal Lane from just east of Preston Road to Jamestown and another crew for the installation of new water mains along Preston Road starting at Walnut Hill Lane and moving north to Royal Lane.  For water main construction along Preston Road, no lane closures are expected since the pipeline is being installed in the parkway using trenchless, directional drilling methods.  At Royal Lane, no more than one lane closure is expected for the water and wastewater main installation.  The overall estimated completion schedule for both Preston Road and Royal Lane is Fall 2019, weather permitting.For more information, please click the following link:  State Highway 289 Preston Road

  • Dallas Water Utilities has a pipeline replacement project in the easement south of Orchid Lane from SH289 (Preston Road) East (PID 4957). DWU contractor is in the process of scheduling final paving restorations. Entire project including final paving and surface restoration is expected to be complete in Summer 2018, weather permitting.

  • Dallas Water Utilities has a pipeline replacement project in the easement west of Camellia Drive from State Highway 289 (Preston Road) to north of Royal Lane (PID 4954). DWU contractor has finished pipeline installation and currently is in the process of completing water testing, sampling and service tie-ins. Entire project including final paving and surface restoration is expected to be complete in May 2018, weather permitting.

  • Dallas Water Utilities has a pipeline replacement project on Royal Lane from Cromwell Drive West (PID 4616). DWU contractor has completed the utility construction and paving restoration. The contractor is in the final stages of replacing sod impacted by construction.  Project is expected to be complete in April 2018.

  • Dallas Water Utilities has a pipeline project on Royal Lane from Cox Lane east (PID 2534). Work is scheduled to start in April 2018 and be completed in Fall 2018.

  • Dallas Water Utilities is constructing new water and wastewater mains on Prestonshire Lane  from Edgemere Road to Hillcrest Road (PID #5531). DWU contractor has finished pipeline installation and has been released to complete final paving restoration. Entire project including final paving and surface restoration is expected to be complete by late May 2018, weather permitting. For more information, please click the following link: Prestonshire Lane