“Storm Drainage Improvements: MILL CREEK / PEAKS BRANCH / STATE-THOMAS STORM DRAINAGE RELIEF TUNNEL”
Trinity Watershed Management, 1500 Marilla St., 6BS, Dallas, TX 75201
Pre-Bid meeting will be held on Tuesday, October 6, 2015 at 9:00 a.m., at City Hall, 1500 Marilla Street, Conference Center Auditorium, L1EN. Attendance of all prospective bidders is strongly encouraged. Plans, specifications, and other related material may be obtained at the Oak Cliff Municipal Center, 320 E. Jefferson Blvd., Room 307, Dallas, TX 75203. Cost is $15.00 (non-refundable) per USB jump drive which contains Plans, Specifications, Geotechnical Baseline Report, and Geotechnical Data Report.
The Mill Creek/ Peaks Branch/ State-Thomas M/WBE meeting that was held on September 18th, 2015 is now available for viewing :http://dallastx.swagit.com/play/09242015-1158
Contact: Milton Brooks, at 214-671-9500; or milton.brooks@dallascityhall.com
Bid Due Date: Friday, December 18, 2015
Bid Opening Date: Friday, December 18, 2015