Page Content

Public Safety Training Complex​ (PSTC)

Download Fact Sheet

Location

Dallas Executive Airport

Status

Design Complete

What is the Project?OverviewFunding SourcesNov 2026 Ballot Info

What is this project?

The Public Safety Training Complex (PSTC) is a new public safety training facility proposed on 60+ acres at Dallas Executive Airport. The PSTC was not included in the original 2024 Bond Program. The need for a site to house the driving track and simulated village were identified as a separate need in a Dallas City Council Public Safety Committee briefing on November 13, 2023. A feasibility study, presented to City Council on April 15, 2026, reviewed six city-owned parcels and identified Dallas Executive Airport as the most viable site. The complex is planned to include:

  • An Emergency Vehicle Operations Course (EVOC) : Training area for safe, controlled emergency driving and maneuvering;
  • Skill and Skid Pads: Surfaces to practice vehicle control in slippery or challenging conditions;
  • Simulated Street Grid: Mock city streets for realistic emergency driving and response training;
  • Outdoor Tactical Village: Realistic setting for practicing coordinated tactical and rescue operations;
  • Firearm Ranges: Safe, controlled spaces for authorized firearm training and proficiency;
  • Obstacle Course: Physical challenge area for building strength, agility, and endurance;
  • Support Buildings: Facilities housing classrooms, offices, equipment, and essential training services;
  • Parking: Designated areas for staff, trainees, and visitor vehicles.

Overview

Need

Would house DPD driving track, firearm range, and simulated tactical training village

Funding

This project received no funding from the 2024 Bond Program

Site

Proposed location 60+ acres at Dallas Executive Airport​

$170M

Total project cost

$21M

Amount already identified ​(enabling infrastructure and sponsorship)

$149M

Amount proposed for the Nov. 2026 Bond

Funding Sources

The table below shows the funding identified and what the proposed November 2026 Bond would provide toward the $170M total funding need.

  • $15M

    AVI (airport) enabling infrastructure

  • $6M

    Anticipated Sponsorship

  • $149M

    Proposed Nov. 2026 Bond

    (unfunded portion)

  • $170M

    Total funding need

How This Fits Into the November 2026 Ballot

The $149M unfunded portion of this project would be funded through City of Dallas Proposition A — Public Safety Facilities, a proposed $443M general obligation bond authorization. Proposition A is also planned to fund several other public safety facility projects not covered in this fact sheet, including the Dallas Police Department (DPD) Law Enforcement Training Center, an Emergency Operations Center/911 Facility, a consolidated DPD Property Room, Evidentiary Vehicle Storage Facility and Crime Lab, and Fire Station No. 4 replacement.

Total amount being considered by voters is $443M for Proposition A. Under Texas law, the official ballot language for this proposition is required to state: “This is a tax increase”; however, the city’s tax rate will not increase related to this bond program​. The estimated repayment for all of Proposition A, including principal and interest, is $629,618,180 over a term not to exceed 20 years.


Title