DWU Pipeline Project Updates – Council District # 13
 

  • Dallas Water Utilities has a pipeline replacement project in the Easement west of Camellia Drive from State Highway 289 (Preston Road) to north of Royal Lane (PID 4954). DWU contractor has finished all utility work and final paving restorations. The only work left is the repair of minor deficiencies related to the final paving. Entire project is expected to be complete in February 2019, weather permitting.  

 

  • Dallas Water Utilities has a pipeline replacement project on Chadbourne Road from Caruth Boulevard to Stanford Avenue (PID 5632). DWU contractor has completed 100% of the wastewater main and 70% of the water main. Entire project including final paving and surface restoration is expected to be complete in March 2019, weather permitting.

 

  • Dallas Water Utilities has a pipeline replacement project on State Highway 289 (Preston Road) from Walnut Hill to Royal Lane (PID 4953). DWU contractor has completed about 75% of wastewater mains and is scheduled to start water main installation by the end of February 2019. Entire project including final paving and surface restoration is expected to be complete in Fall 2019, weather permitting.

 

  • Dallas Water Utilities has a pipeline replacement project on Townsend Drive from Cox Lane to Vinecrest Drive (PID 5498). DWU contractor has completed all utility work. Entire project including final paving and surface restoration is expected to be complete in February 2019, weather permitting. 

 

  • Dallas Water Utilities has a Pump Station and Reservoir Improvement project at the Walcrest Pump Station located at the northeast corner of Hillcrest and Walnut Hill. DWU contractor is scheduled to commission the new pump station and reservoir 1 in Spring 2019.  The second reservoir will be completed by Fall 2019, followed by site landscaping improvements to begin late 2019, weather permitting. More detailed information and updates are available at www.walcrest.org