District 1


Project Updates

​There are several ongoing City projects of interest to District 1 residents.  First,  there is the reconstruction of Sylvan Avenue, north of I-30.  This project is located in adjacent Council District 6, but affects a vital route in and out of north Oak Cliff.

The Tyler-Polk Two-way Conversion project will change those streets from one-way to two-way and will include updates to traffic signals  from Davis St to Twelfth St.

The West Davis project will partially reconstruct the street while improving pedestrian features between North Clinton Ave and Cedar Hill Ave.

Finally, Fort Worth Avenue from Sylvan Ave to W Commerce St will include pedestrian improvements, the addition of bike lanes and partial reconstruction of the street.

Below  is information about the status of each project, as well as links to select project plans. The status information will be updated on this page each week.

Plans:

Sylvan Avenue Reconstruction

Tyler/Polk Two-way Conversion Plans (PDF, 61 MB)


Project Updates - January 15, 2019: 

Sylvan Ave.:

  • Project name:   Sylvan Avenue from Fort Worth Avenue to Singleton Boulevard (PB06U802)
  • Scope of work:  Includes reconstructing Sylvan Avenue to 4 lane divided with bike lanes, with 10-inch thick reinforced concrete pavement, storm drainage, water and wastewater main replacement.
  • Construction cost:   $7,663,718
  • Construction start:  August 1, 2017
  • Estimated construction complete:   Winter 2019           

Project Construction Complete, in Warranty Period.

Tyler/Polk Two-Way Conversion: 
  • Project name:   Tyler/Polk Two-Way Conversion (PB06P894)
  • Scope of work:  Converting Tyler St. and Polk St. from Canty St. to Pembroke Ave. to two–way streets by constructing a traffic roundabout on Tyler St. and Polk St. from Canty St. to Winston St. and a  new traffic signal south of the Tyler/Polk/Page intersection; install new pavement markings and traffic regulatory signs to accommodate the two–way conversion; replace all existing traffic signals on Tyler St. and Polk St. from Davis St. to Twelfth St.; and replace existing water & wastewater facilities under Tyler St. and Polk St. from Canty St. to Winston St.
  • Construction cost:   $6,442,097
  • Construction start:  January 2020
  • Estimated construction complete:   April 2021           
  • Design Completed:  February 2019
  • Advertisement: March 6, 13 & 20, 2019
  • Opened Bids: April 5, 2019
West Davis Street: 
  • Project name:   West Davis Street from North Clinton Avenue to Cedar Hill Avenue (PB12S405)
  • Scope of work:  Includes partially reconstructing West Davis Street from North Clinton Avenue to Cedar Hill Avenue, with 10-inch thick reinforced concrete pavement and 2-inch asphalt overlay, pavement markings, on-street parking, wider sidewalks, barrier free ramps, LED pedestrian lighting, trees, and stormwater inlet replacement.
  • Construction cost:   $3,016, 209.50
  • Construction start:  March 18, 2019
  • Estimated construction complete:   March 2020           

Accomplishments for the week of January 9, 2020 to January 15, 2020:

       •      Completed the excavation/sawcut work on the south side of West Davis Street from S. Polk Street to Willomet Avenue; and

       •      Surface milled the south side of West Davis Street from Clinton Avenue to S. Polk Street; and

  • Installed forms to prepare for the paving work on the south side of West Davis Street from S. Polk Street to Willomet Avenue; and
  • Additional survey work was done to verify some of the information provided in the plans

Planned tasks for the week of January 16, 2020 to January 22, 2020:

  • Place concrete paving on the south side of West Davis Street from S. Polk Street to Willomet Avenue; and
  • Begin replacing sidewalks and driveway approaches on the south side of West Davis Street from S. Polk Street to Willomet Avenue; and
  • Begin installing pedestrian light poles on the south side of West Davis Street from S. Polk Street to Willomet Avenue
Fort Worth Avenue:
  • Project name:   Fort Worth Avenue from Sylvan Avenue to West Commerce Street (PB06P838)
  • Scope of work:  Includes reconstructing Fort Worth Avenue from Sylvan Avenue West Commerce Street to 4 lane divided with bike lanes, with 11-inch thick reinforced concrete pavement, storm drainage, water and wastewater main replacement, new traffic signal at Fort Worth Avenue and Sylvan Avenue, pavement markings, wider sidewalks, barrier free ramps, LED street lighting, LED pedestrian lighting, trees.
  • Construction cost:   $4,991,975.50
  • Construction start:  July 2019
  • Estimated construction complete:   January 2021           

Accomplishments for the week of January 9, 2020 to January 15, 2020:

  • The water testing results have been approved for the connection of the new main water line; and  
  • Waiting on Dallas Water Utilities Valve Group to schedule the tie-In of the new water
Planned tasks for the week of January 16, 2020 to January 22, 2020:
  • Cut out the old water main and connect the new water main at Yorktown Street and Commerce Street; and
  • Continue with removal of underground stormwater; and
  • Continue with stormwater installation along the south side of Fort Worth Avenue.