District 1


Project Updates

​There are several ongoing City projects of interest to District 1 residents.  First,  there is the reconstruction of Sylvan Avenue, north of I-30.  This project is located in adjacent Council District 6, but affects a vital route in and out of north Oak Cliff.

The Tyler-Polk Two-way Conversion project will change those streets from one-way to two-way and will include updates to traffic signals  from Davis St to Twelfth St.

The West Davis project will partially reconstruct the street while improving pedestrian features between North Clinton Ave and Cedar Hill Ave.

Finally, Fort Worth Avenue from Sylvan Ave to W Commerce St will include pedestrian improvements, the addition of bike lanes and partial reconstruction of the street.

Below  is information about the status of each project, as well as links to select project plans. The status information will be updated on this page each week.

Plans:

Sylvan Avenue Reconstruction

Tyler/Polk Two-way Conversion Plans (PDF, 61 MB)


Project Updates - May 22, 2019:

Sylvan Ave.:

  • Project name:   Sylvan Avenue from Fort Worth Avenue to Singleton Boulevard (PB06U802)
  • Scope of work:  Includes reconstructing Sylvan Avenue to 4 lane divided with bike lanes, with 10-inch thick reinforced concrete pavement, storm drainage, water and wastewater main replacement.
  • Construction cost:   $7,663,718
  • Construction start:  August 1, 2017
  • Estimated construction complete:   Winter 2019           

 

Accomplishments for the week of May 16, 2019 to May 22, 2019:

  • Continued with west parkway pedestrian improvements (west side of Sylvan Avenue);
  • Continued with stamped colored crosswalk on west side of Commerce Street at Sylvan Avenue; and
  • Continued with paving west side of Commerce Street at Sylvan Avenue.

 

Planned tasks for the week of May 23, 2019 to May 29, 2019:

  • Perform hydrostatic test of 12-inch waterline at Commerce Street, having previously replaced a water main segment (on east side of Sylvan Avenue at Commerce Street);
  • Complete placing concrete roadway pavement above newly replaced water main segment (on east side of Sylvan Avenue at Commerce Street);
  • Continue with west parkway pedestrian improvements (west side of Sylvan Avenue); and
  • Complete the stamped colored crosswalk on west side of Commerce Street at Sylvan Avenue.

 


Tyler/Polk Two-Way Conversion:

  • Project name:   Tyler/Polk Two-Way Conversion (PB06P894)
  • Scope of work:  Converting Tyler St. and Polk St. from Canty St. to Pembroke Ave. to two–way streets by constructing a traffic roundabout on Tyler St. and Polk St. from Canty St. to Winston St. and a  new traffic signal south of the Tyler/Polk/Page intersection; install new pavement markings and traffic regulatory signs to accommodate the two–way conversion; replace all existing traffic signals on Tyler St. and Polk St. from Davis St. to Twelfth St.; and replace existing water & wastewater facilities under Tyler St. and Polk St. from Canty St. to Winston St.

 

  • Construction cost:   $3,716,000.00 (estimate)
  • Construction start:  To be determined (funding)
  • Estimated construction complete:   To be determined (15 month construction duration)           
  • Design Completed:  February 2019
  • Advertisement: March 6, 13 & 20, 2019
  • Open Bids: April 5, 2019

 

 

West Davis Street:

  • Project name:   West Davis Street from North Clinton Avenue to Cedar Hill Avenue (PB12S405)
  • Scope of work:  Includes partially reconstructing West Davis Street from North Clinton Avenue to Cedar Hill Avenue, with 10-inch thick reinforced concrete pavement and 2-inch asphalt overlay, pavement markings, on-street parking, wider sidewalks, barrier free ramps, LED pedestrian lighting, trees, and stormwater inlet replacement.
  • Construction cost:   $3,016, 209.50
  • Construction start:  March 18, 2019
  • Estimated construction complete:   February 2020           

 

Accomplishments for the week of May 16, 2019 to May 22, 2019:

  • Commenced sidewalk preparation on north side of West Davis Street from Van Buren Avenue to Cedar Hill Avenue;
  • Commenced with irrigation system installation on north side of West Davis Street from Van Buren Avenue to Cedar Hill Avenue;
  • Completed tree well soil backfill on the north parkway from Vernon Avenue to Cedar Hill Avenue; and
  • Continued with installation of underground electrical conduit and pedestrian lighting foundations along north parkway of West Davis Street from Vernon Avenue to Cedar Hill Avenue.

 

Planned tasks for the week of May 23, 2019 to May 29, 2019:

  • Continue with sidewalk preparation on north side of West Davis Street from Van Buren Avenue to Cedar Hill Avenue;
  • Continue with irrigation system installation on north side of West Davis Street from Van Buren Avenue to Cedar Hill Avenue; and
  • Continue with installation of underground electrical conduit and pedestrian lighting foundations along north parkway of West Davis Street from Vernon Avenue to Cedar Hill Avenue.

 

 

Fort Worth Avenue:

  • Project name:   Fort Worth Avenue from Sylvan Avenue to West Commerce Street (PB06P838)
  • Scope of work:  Includes reconstructing Fort Worth Avenue from Sylvan Avenue West Commerce Street to 4 lane divided with bike lanes, with 11-inch thick reinforced concrete pavement, storm drainage, water and wastewater main replacement, new traffic signal at Fort Worth Avenue and Sylvan Avenue, pavement markings, wider sidewalks, barrier free ramps, LED street lighting, LED pedestrian lighting, trees.
  • Construction cost:   $4,991,975.50
  • Construction start:  June 2019
  • Estimated construction complete:   December 2020