There are several ongoing City projects of interest to District 1 residents.
Below is information about the status of several major projects.The status information will be updated on this page each week.
Plans:
Project Updates - June 9, 2023:
Kidd Springs Park Japanese Garden
- Project name: Kidd Springs Park Japanese Garden (PKR-2021-00016987)
- Scope of work: Creating an ADA accessible route through the garden, replacing the pedestrian bridge, foot bridge, north and south water features and entry portals.
- Construction cost: $1,099,915.10
- Construction start: March 23, 2022
- Estimated construction complete: March 2023
- Design Completed: April 7, 2021
- Advertisement: May 5, 2021 & May 12, 2021
- Opened Bids: June 18, 2021
Jefferson-12th Street Connector
- Jefferson-12th Street Connector:
- Project name: Jefferson-12th Street Connector (PB17V990)
- Scope of work: Removing the Jefferson-Twelfth Connector and replacing it with Kevin Sloan Park, which will include hardscape/landscape, lighting, crosswalks, trash receptacles, benches, and trail paths; new concrete pavement for Clinton Ave, Winnetka Ave, and Willomet Ave; extend existing alleys so each side has an alley approach to Jefferson Blvd and Twelfth Street, Water and Wastewater line replacement
- Construction cost estimate: $4,000,000
- Construction start: August 2023
- Construction Days allowed: 395
- Design Completed: December 2022
- Advertisement: February 24, 2023, March 1 ,8, & 15 2023
- Opening Bids: March 17, 2023
- Construction contract award: May 24, 2023
- Construction start: August 2023
- Construction days allowed: 395
Main activities performed last week and planned activities for next week:
We are currently processing the construction contract for execution.